The difference between a prime cost sum and a provisional sum
Contents |
[edit] Introduction
There is sometimes confusion regarding two items that may appear in standard forms of building contract – prime cost sums (PC or PC sums) and provisional sums (PS). They both relate to allowances made for certain costs in the absence of exact figures, but they are actually quite different.
[edit] What is a prime cost sum?
A prime cost sum is an allowance, usually calculated by the cost consultant, for the supply of work or materials to be provided by a sub-contractor or supplier that will be nominated by the client - that is, a sub-contractor or supplier that is selected by the client to carry out an element of the works and imposed on the main contractor. The main contractor is entitled to add mark up and attendance costs to the allowance.
Actual payments are made based on the quotations/invoices of the supplied items plus the addition of reasonable/agreed percentages for overhead costs and profits.
If the main contractor's actual costs then turn out to be higher, the contract sum is increased, and if the main contractor's actual costs are lower, the contract sum is reduced.
For more information see: Prime cost sum.
[edit] What is a provisional sum?
A provisional sum is an allowance, usually estimated by a cost consultant, for a specific element of the works that has not been defined in enough detail at the time that prices are sought from tenderers, for those tenderers to accurately price them. Provisional sums are replaced by valuations of the work actually done as the project progresses and so the contract sum may increase or decrease.
Depending on the degree to which the works that the provisional sum relates to can be described at the tender stage, provisional sums may be referred to as 'defined' or 'undefined'.
- Defined provisional sums are those which have been described in sufficient detail for the tenderer to make allowance for them in their programming, planning and pricing preliminaries.
- Undefined provisional sums are less well described and so the tenderer cannot be expected to make allowance for them in their programming, planning and pricing preliminaries.
For more information see: Provisional sum.
[edit] Summary
In summary, both provisional sums and prime cost sums are allowances for items that cannot be accurately priced when tenders are sought. Provisional sums relate to items for which there is insufficient information - such as earthworks for example, where it may be difficult to determine what is required before some excavation has been undertaken, whereas prime cost sums relate to suppliers or sub-contractors that are nominated by the client, such as specialist equipment suppliers for example.
As both add a degree of uncertainty to the contract sum, they should generally be discouraged.
[edit] Related articles on Designing Buildings
Featured articles and news
About the 5 Percent Club and its members
The 5% Club; a dynamic movement of employers committed to building and developing the workforce.
New Homes in New Ways at the Building Centre
Accelerating the supply of new homes with MMC.
Quality Planning for Micro and Small to Medium Sized Enterprises
A CIOB Academy Technical Information sheet.
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Comments
[edit] To make a comment about this article, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
Is PC for a specific element? It seems that it does not match the Home Building Contract?
It is for a specific element of the works. This is a term used in the UK, it may be that definitions / contract terms are different in other countries.
That's so vague
As with all construction terms, the exact definition will depend on the contract that is being used.